Gabon: up to a quarter of the cost of wood is moving it.

15–25%of the cost of producing wood goes on logistics
64 dayswood can wait at the production site
4×the normal time: what a journey can take
⅓of the road network, almost, is unpaved

Figures from the study, rounded.

A processing industry needs its raw material on time and its product at the port on time. In Gabon both hauls are slow and dear, for wood and for manganese alike, and that decides whether processing at home can compete.

What the work found

Roads

Almost a third of the network is unpaved, and often impassable in the rains.

The port

Shallow water, few vessels, limited opening hours and complex customs. Costs at the port are rising.

Paperwork

Export clearance is not yet digital, and policy is uncertain.

Power in the processing zone

The zone uses 28 of the 60 megawatts available to it, and firms still rely on diesel generators.

Who pays for what

Projects with a high return and a high effect on the industry go to private investors. Those with a low return and a high effect are for development finance.

What it calls for

  1. A bypass to the portFrom the national road, for the trucks that carry wood.
  2. Rail and river beside the roadTransfer points where wood moves between road, rail and river.
  3. A port that works all yearWorks for the shallow water, and simpler procedures.

One of the value-chain studies behind the partnership strategies our team led.